Hi All,I am working on dynamic workflow and i need to activate 2 task on action with User task- for e.g. link_tasks(task1(cgitask),task2(externaltask),"comments");This task2 will have to activate 2 tasks namely, task3(usertask) and task4(dummytask).link_tasks(task4,task5(externaltask),"comments");task3 can again call task1 or task5How can i activate task3 and task4 after task2 in dynamic?Thanks in advance
Use identical successorset description in both linking.link_tasks(task2, task3, 'Activate Concurrently');link_tasks(task2, task4, 'Activate Concurrently');
Yeah.. it worked....Thanks much
What you are changing??