Hi All,
We are using workflow modeller 1.0.0.1 with teamsite 6.7.1 SP1. We have following requirement for the workflow:-
There are two parallel review tasks. Owner of first review task (say task A) is a user and owner of second review task (say task

is reviewer group. Following are the flows for these tasks.
1. If both tasks are approved then it will go to FLOW A.
2. If both tasks are rejected, then it should go to Flow B.
3. If any task is rejected, then it should go to Flow B but it should wait for completion of other parallel task before going to flow B (for example, if task A is rejected then it should wait for completion of task B, before going to flow

.
Condition 1 and 2 can be achieved by using AND gate.
But the problem will occur when one task is approved and another is rejected (say task A approve and task B rejected). In this case none of the AND condition will be satisfied and workflow will hang.
I tried to use a combination of AND, OR gate but not able to achieve our requirement.
Any help/pointer in this regard will be appreciated.
Thanks
A.S.