Gantt Chart comparing Project baseline to actual

UtahJerry
UtahJerry Member
edited February 11, 2022 in Analytics #1
<p>I need to create a chart that compares baseline to actual for several projects in a gantt chart format.  I have created a 'work around' by building a query that creates separate rows for the baseline and actual data.  I created series for all of the project phases and added an additional series to draw a 'Today' line.  (See Attached)  This correctly reports the data, but the users complain because it doesn't group the baseline and actual for a project in a way that makes a project clearly stand out.  </p>
<p> </p>
<p>Is there a better way to display a pair of baseline and actual data or at least separate the pairs into clear 'sets'?</p>
<p> </p>