keith999
I have the following scenario which required two approvers to approve tasks before it goes to next task.
1. Job initator (JI) submits a job
2. Approver A approves task A in a Job
3. Approver B rejects task B in the same job
4. The job returns back to JI.
5. JI resubmits the same job
6. Approver B approves the job
7. Approver A takes no action this time.
8. The job activates task C without approver A's approval.
Problem
I expected task C will only be activated if task A and task B are both approved. When an approver rejects a task as step3 above, task A and B are set to inactivate with workflow elements "inactivate"
However, it seems that it does not work properly. Task C can still transit
to its successors even task A is inactive.
Question
1. How the "inactivate" element can reset a task status to inactive status
(not approved)?
2, If "inactivate" elements cannot reset the status, what other elements
can be used?
3. I have tried to use "Resets" elements but it doesn't work either. What is the difference between the two.
Find more posts tagged with
Comments
Jeremy
Hi,
Could you possibly post the code itself? There might be a problem with the consitancy of the successors/predecessors. Would help to debug with the WFT.
Thanks,
Jeremy
james1
<inactivate> simply tells another (active) task to go inactive (without transitioning to successors).
<reset> tells another task to clear its activation data. In your case, task C knew that task A had transitioned to it (in the first review cycle). In the second review cycle, task B transitioned to task C, and (assuming task C's activation criteria was "A and B") then task C decided it was time for it to activate, as its criteria was finally satisfied.
On rejection, you want task C to be reset, so that it forgets about the approvals that happened in the previous cycle. In other words, you want the JI task to inactivate A and B, and to reset C.
-- James
--