Modeling
Hi All
I am trying to do simulation in provision.
I have given source volume to be 300 and decision box with distribution of 80/20. Entire 300 volume is not getting processed and is stopping after 160.
I have tried changing options of running time and arrival rate etc.
any help will be greatly appreciated !!
Sidharth
Tagged:
0
Comments
-
Hi Sidharth,
Are you using Monte Carlo Simulation or Discrete Event Simulation? For further investigation would you be able to submit a case and share a copy of your data (and tell us which particular workflow you're running your simulation against)?
Regards,
Matt Michael0
Categories
- All Categories
- 123 Developer Announcements
- 54 Articles
- 153 General Questions
- 148 Thrust Services
- 57 Developer Hackathon
- 37 Thrust Studio
- 20.6K Analytics
- 4.2K AppWorks
- 9K Extended ECM
- 918 Core Messaging
- 84 Digital Asset Management
- 9.4K Documentum
- 32 eDOCS
- 190 Exstream
- 39.8K TeamSite
- 1.7K Web Experience Management
- 10 XM Fax
- Follow Categories